Please inform the status of electric grid station work at DHA Phase 9 Prism M ZahidŽ replied on Tuesday, January 9, 2018 10:30 AM
Grid station equipment lead time is the major factor after placing the contract. 8 to 15 months is the normal time for manufacturing to installation. Civil works is minor and only few months. There is no visibility on ground of any civil works for grid till December when i visited. |