There is hardly any development work going on in sector D-12 and neither had it looked like it is going to start soon. But the staff on site does admit that the dispute between CDA and contractor is almost resolved When I asked the question to the deputy project manager of Ayub Brothers Co. Mr Azam to explain “ resolved “ he and two staff member of CDA said to assume 70 : 30.
I asked when you are actually going to mobilizes on site and bringing all of your crew and machinery he said within this week. The contractor admits that all area of D-12 is acquired apart from the two houses coming in the way of south service road.
I visited this sector after almost 8 months and the difference from then to now is almost nothing if there is a development there are certain areas got washed away as well by rain
I doubt the capability of contractor and believe he will take much more then a year for remaining works unless he has come back with a total different attitude.
I will keep updating if there is any such improvement. :flg