DHA Lahore Development work update,

(52422)
Saturday, April 11, 2009 11:48 AM 

Dear friends I am very sorry for not updating you on regular bases about development status of DHA Lahore. I am busy these days with building my dream house.


I will try to update you with pictures in next 3 to 4 days time.

DHA phase 5 K and L block development is almost 100% completed. I expect DHA to hand over DHA 5 K and L block as soon as next month. Get ready to build your house in K and L blocks from May 2009.


DHA 6 F block is now ready for house construction. You could check wih DHA if your plot is in possession or not. Although not officially announced yet but DHA 6 F block is now open for possession and house constructions.


DHA 6 N M and L blocks will insahAllah have possession from June 30th 2009.


Defence Raya Phase 6 golf course houses are under rapid construction. I expect all house of DHA defenceraya phase 1 to be handed over by Dec 30th 2009.

Ring road construction speed have increased once again after Shehbaz Sharief Govt restoration. Even part from GT road to canal bank is now under very rapid construction. Work is expected to start soon on interchange and underpass of DHA 5 - 6.

Ch Mujahid Yasin ( CMY )
0322-4009967
042-111-111-040

cuckoo replied on Saturday, April 11, 2009 12:01 PM 

CMY Sahib what about E block possession time.

Sarwar replied on Saturday, April 11, 2009 12:04 PM 

Intend to buy a plot in Phase-6, F-block, but my total budget is 40 lac. Is it possible to get it on this rate? Thanks and regards

adnan replied on Saturday, April 11, 2009 12:26 PM 

Dear CMY sb

Good day

Any news for DHA phase 7 remaining block(development)
We are paying develipment charges but no good news
even you have stopped mentioninr rates for Phase 7

Rgsd

Zahid Bhalli replied on Saturday, April 11, 2009 01:42 PM 

Dear Brother CMY,
Many congratulations on the construction of your dream house. May Allah SWT bless you with many more sucesses. A long healthy & shining life to live happily with your family. ( Ameen )

CMY replied on Saturday, April 11, 2009 05:09 PM 

Zahid sahib thanks for you best wishes.

Adnan bhai R S T U and part of Q will be ready for house before Dec 31 2009. My market research is telling me some plots in R Q ( Near Berki road plots) will be relocated near possession time due to litigation issues in Q and grave yard in R. My research is also telling me MOST of Z block plots and Some of Y block plots along with all10 marla plots in DHA 7 will be relocated and there is a strong possibility of all these plots will be relocated under T and U blocks in currently under development areas. This is a great news of all holders for these lowest priced plots. You cant get worst location after this relocation in my opinion. X W V and part of Y development should start any time during next 3 to 6 months. R block could have possession in June 2009 with E block.

Please please please don't buy or sell any thing base don my info here. You must verify many things from your own sources to make all buy sell decisions.

There are 5 houses under construction in DHA 6 J block, 2 in H block, one in C block ,one in D block, 8 in A block. Dozens of new houses constructions are expected to start in A B H J and C plus G blocks in next 3 to 6 months time.


Ch Mujahid Yasin ( CMY )
03224009967
042-111-111-040

CMY replied on Saturday, April 11, 2009 05:16 PM 

Sarwar bhai currently its very hard task but I belive its very possible before budget announcment.

Please call me or send me your phone number in email at LahoreRealEstate@Gmail.com so I could call you after finding some plot that can fit your your budget. Last week I bought a 70 feet road corner for a friend at 42.50 lacs in F block. May be If I work hard enough I should be to find a non corner plot for you near 40 lacs in coming days. If you get lucky it will happen before the budget.

Ch Mujahid Yasin ( CMY )

042-111-111-040

CMY replied on Saturday, April 11, 2009 05:26 PM 

Bahria Town Lahore is now also getting populated faster than past. House construction every where. Its changing from just a scheme to a town now. People are very comfortable to start a new house there. Bahria town Orchard is also getting popular more and more every day after people make their visit there.

NFC phase 2 development is now on going and they are now working on main boulevard.

Central Park is getting more life too and lot of development can be seen on ground and more progress is happing day by day.

State Life phase 2 development is still dead. Nothing new about map or development. Some one is needed to wake people in charge in this case.

Ch Mujahid Yasin ( CMY )
03224009967
042-111-111-040

Ch Mujahid Yasin ( CMY )

A. Khan replied on Saturday, April 11, 2009 06:42 PM 

Dear Brother CMY,
Congratulations on the construction of your dream house. It is not easy to built a house in Pakistan especially for those who has no past experience in construction.
Please share lesson learned you might have learned during construction of your house. This will be very helpful for people who wants to construct their house first-time, but has no past experience. Anything you can share from design of your house to material used in the construction, to labor problems or contracting out construction etc, just about anything that might help anyone who is constructing first time.

Imran replied on Saturday, April 11, 2009 06:53 PM 

Drear respectable Cmy,
please tell about phase 7 P block development update waiting.thanks

Sarwar replied on Sunday, April 12, 2009 03:58 AM 

CMY Sb: My email address is :

adnan replied on Sunday, April 12, 2009 04:35 AM 

Dear CMY
Thanks alot for the updates
after so many years Finally a GOOD NEWS FOE Z BLOCK
I am holding polt1391 /Z Phase 7

Best regards

FM replied on Sunday, April 12, 2009 09:25 AM 

Dear CMY,

I have a plot on main 150 feet road that goes to golf course. Is there any chance of these plots being relocated also? It would be a bad news for me as I bought at a quite a high price.

Kind Regards

limo replied on Sunday, April 12, 2009 10:49 AM 

CMY, it is good to hear that your "dream house" construction is underway.Please do share your experience in this regards and also tell which area of Lahore this activity is going on.

CMY replied on Sunday, April 12, 2009 04:44 PM 

Friends I am in very early stage of this scary process of building a house in Pakistan :)

I am documenting every thing from day one but I will try to share it with you when full house is completed.

Ch Mujahid Yasin ( CMY )
042-111-111-040
0322-4009967
>