DHA ISLAMABAD LATEST SATUATION OF NEWLY LAUNCHED PROJECTS,

(56196)
Saturday, January 9, 2010 09:28 AM 

Now come to the DHA ISLAMABAD Project which are newly launched and see their progress.

DHA EXPRESS WAY
this is approach road for DHA phase-2 extension & Valley.
Mr. imran said "DHA Expressway (8.2 km, 6 lanes) are near to completion, with some work remaining on bridges/crossways."
if one go to site he can see that earthwork at different patches is started. road is only carpeted at start about 400 meters. bridges and culverts are to be prepared. It is started 8 month before and still minimum one year is required to finish the work.

DHA DHA OVERSEAS Project
It is satuated near Sawan Bridge. It is between Kahota Road and Ex-Commoners town. It is started 4 years ago but Only the gate and 500 Meter main entrance road is constructed. And marketing office is prepared.
This is a separate project from Valley and Phase-2 extension. So, don't mix it with these projects. Although DHA phase-2 Extension and Valley has their Overseas Sector but i am not discussing it here.
Mr. imran did't write about this project. Because he can't defend it. This block is introdused only to trap the overseas pakistani and to get dollers.

DHA PHASE-2 EXTENSION
DHA phase-2 extension has more than 70 thousand kanals area. Only one Road of 500 meter is in process which is linked with Instustrial Road. This road is named "Industrial Link Road" and still not carpetted.
Mr. imran said "Development work is under process. The earlier the sector (out of 4) the sooner the possession is expected."
He is giving false hopes of possessions. Just to Silent the people and stop their angreeness. Can DHA give possesion on Raw land like Jungle while there is no road prepared. If DHA start one sector of this project today with full pace then possession is possible after 4 years. then thick about other 3 sectors yourself. While DHA is also failed to made the New Replanned Map of this project in which they divided it in 4 sectors.

DHA VALLEY
It is divided into 20 sectors and it has plots more than one lak according to the issued map. It has more than one lak kanal area. No work is in progress in any sector. The work is in progress in a land called DHA Homes along expressway.
People think it DHA Valley. Mr. imran put DHA Homes in DHA Valley and shows the progress in DHA Valley.
While DHA Homes is a seprate scheme and Valley is seperate scheme.
Mr. Imran! if you dont have correct information than please don't confuse people.

DHA HOMES
The small peace of one thousand kanal area earthwork is in progress in which DHA want to build houses.

DHA Valley, DHA Phase-2 Extension and DHA Homes will be deveoped by Joint Venture of Habib Rafiq Private Limmited, Bahria Town and DHA. Habib rafiq is devloper, Bahria Town is financer and DHA is Supervisor or Client. But You see ne Year progress then It will take more than 10 years to complete.
Bahria town has his Own priorities. If Malik riaz stop spending money then what will DHA do? because DHA have no money to spend.

Mr. Imran did't deny in his post no. 45888 about the fact i wrote in my previous post no. 45832 but he said the same things i said before. He just added some hopefull senctences in each project detail that possession will soon be given.

SALEEM AWAN replied on Saturday, January 9, 2010 04:11 PM 

No other Contractor company is willing to work with DHA Islamabad. EMMAR (UAE) left the job. IJM, Bina Goodears from malysia left teir jobs also.
Only Habib rafiq is working on development of DHA projects. Their money is also blocked in DHA projects and company is near to defalut.HRL money has also blocked in DHA projects and work is stopped at all projects expect DHA Expressway and DHA Homes which is financed by Bahria Town. I am loyal to DHA but in know the exact situation and i don't want that DHA should loot the Hard earned money of Pakistani People.
People should make Case in Courts about completion of these projects as well as about the Additional development charges charged to them with time by time.
My Suggestions to DHA official.
1. DHA should spent money on the projects for which they have collected the money from plot members.
2. Work pace should be kept fast.
3. Instate of Huge project like DHA Valley & Phase-2 Extension of 1.5 laks kanal area, they should launch project having only 10 thousand to 15000 kanal area like Phase-2 and Ex-Commoners town. They should build smaller portion and give possessions and then start new portion rather they Launch those huge area project more than the area of Islamabad which will never be completed in time and will take decays.
The 10 years is minimum for those projects which i told. Looking to current pace of work it can take 20 to 30 years estimated.
4. At least Maps of the project should be finalized before launch of any project.
5. The file system should be eliminated. Only plot should be sold. The file means no plot.
6. DHA should stop acquiring the land forcedly from people to build the scheme.
7. Every Project Time period should be given before start and the time period should be strictly monitored by them.

Riaz replied on Monday, August 9, 2010 12:17 PM 

Ref DHA Valley Phase II Extension, I will sue them and let them reply in the court.

Riaz replied on Monday, August 9, 2010 12:23 PM 

Ref DHA Valley Phase II Extension, I will sue them and let them reply in the court.

khalid replied on Sunday, December 26, 2010 01:35 PM 

DHA Valley is still in the heaven and nothing on the spot. It will complete in the year 2090.

Aslam replied on Wednesday, August 17, 2011 04:37 AM 

What about DHA Homes Islamabad. When it will be complete??..

Asif replied on Wednesday, September 14, 2011 03:09 AM 

what about DHA Valley Islamaba. when it will be complete/?
>