Work Details Rate Total Cost Remarks
Labour contractor charges   3,90,000 Your structure will be completed in 60 days
Ghasso   50,000.00 Earth filling
Steel {sarya} per ton ,000.00 "Model steel" Deformed 10 ton includes basement
Cement 334 272, bags
crush Margalla 46/sft 1,20,000 3 trucks Margalla crush
sand 8/sft 60, trolleys
Bricks 5.3 424,,000 bricks
Anti-termite   15,th generation formula
Electrician   20,000.00  
Electric items   170,000.00 Fast cables,Fans,lights,conduting,switches
Plumber   20,000.00  
Sanitary items   89,057.00 Turkish set
Sanitary fittings   82,820.00 Porta,Fasial
Bath tub   6,500.00  
Shower cabin   15,000.00  
Aluminum   150,000.00  
Grills   40,000.00  
Gate   40,000.00  
Terrace railing   30,500.00  
Spiral stairs till roof outside   28,000.00  
Inside SS railing   25,000.00  
Marble cost Botisena   88,790.00  
Flooring Tiles cost 24 inch size 950 24,st floor sitting, kitchen, patio -All imported
Bath tiles 704/ 81,800.00 Master "A" Class from show room
meter
Grinding   26,000.00  
Roof insulation tiles 22 22,000.00 Thermopore 2" thick
False ceiling   34,000.00  
Painter   34,732.00  
Paint/material   71,169.00 ICI factory price
Kitchen Marble slabs   10,000.00  
Kitchen wall tiles   7,000.00  
Main door “Black Gold” Marble Slabs/steps   6,000.00  
Wooden flooring 8mm   25,000.00 Malaysian imported
Carpenter labour charges   72,725.00  
Wooden doors material   79,750.00  
Kitchen wood material   35,680.00  
Elmira wood material   115,910.00  
Door locks   32,290.00 Tower bolts, stoppers, folding handle wire gauge, pipe rods etc
Glass fixer   13,000.00  
Truck/Suzuki rent   10,000.00 For Bath tiles loading, marble tiles, sanitary fittings like commode etc
Bath mirrors   10,000.00 Large glass
Fiber glass   28,000.00 for 2 open roof sections on 1st floor
Bhal/plants   10,000.00  
Graphiato   25,000.00 For exterior paint
contractor charges   600,000.00 House is ready in 6 months Sub totalRs 37,17,17 commencing from S.No 16
Basement cement   66, cement bags in basement size 15'x15' only cement included.
Basement labour charges   70,000.00 To be paid to labour contractor for work
Earthing   5,000.00 Done at the end for safety
3,792,717.00

habib replied on Saturday, April 23, 2011 11:21 AM 

dear
whats the per sq ft charges
what is the difference in A classa nd other class construction

STRANGER replied on Saturday, April 23, 2011 12:00 PM 

Mian Sahib,

Very good effort to bring all the information across.but i think you need to segregate it again in different levels with price so easily any one can understand.
at the moment it gives a mixed picture and not easy to understand people like me who have not done it ever.

Ikram replied on Saturday, April 23, 2011 01:02 PM 

Dear Mr, Rashid,

Is it correct to understand that, total labour approx. cost
will be 300 to 335 rupees per sq.ft.? even more. eg
a. Labour contractor charges =390,000
b. Electrician =20,000
c. Plumbing =20,000
d. Contractor charges=600,000
e. Basement labour charges=70,000
I am sure + many more.

Please revisit your calculation.
Many Thanks

pardesifr replied on Saturday, April 23, 2011 07:42 PM 

That is such a useful post, thank you so much

This gives a clear picture

I have some question :

- What is the Class of this construction ?
- Is the Basement included in your total ? if yes can you please tell me how much the basement cost you alone ?
- Agree with stranger, as you have done so much effort can you give more detail and split in more categories ?

Also if you can tell date and place where it was done ?

Thanks so much, it is already a great effort :)

S.S.S replied on Sunday, April 24, 2011 05:25 AM 

Great,Wunderfull Job......Mian Rashid Sahib.
These are the things needed to the persons newlly starting thire construction are planing.Thanks once more

shiraz replied on Sunday, April 24, 2011 06:10 AM 

Thank you so much Rashid sb for this wonderful information.

It would be great if you can segregate the cost of basement from this. Also please let me know how many bedroom house is this? And what is total covered area?

Mian replied on Sunday, April 24, 2011 06:43 AM 

U can get all the details give ur e.mail add i send u all the details with more clearification

ali1 replied on Sunday, April 24, 2011 08:02 AM 

c0vered area ??????

Mian Rashid replied on Sunday, April 24, 2011 08:58 AM 

U can get all the details give ur e.mail add i send u all the details with more clearification

asif replied on Sunday, April 24, 2011 09:01 AM 

My email address is . Please give details for 1 kanal in Defence phase 6 with basement. Please also comment on the prices/estimate given by pardesi today for A class construction.

Mian replied on Sunday, April 24, 2011 10:06 AM 

ASIF BAHI I SEND U DETAILS PLS CHECK

asghar replied on Sunday, April 24, 2011 01:10 PM 

mjay b detail send ker du.

regards

shiraz replied on Sunday, April 24, 2011 03:37 PM 

kindly also send the details to

Jazaak-Allah

amjad ali replied on Sunday, April 24, 2011 03:50 PM 

plz send me all detail on my e-mail address
thanks

Mian replied on Sunday, April 24, 2011 04:42 PM 

Any one else need pls need e.mail add

mrs arif replied on Sunday, April 24, 2011 07:17 PM 

please also send me details on my e.mail

CS replied on Monday, April 25, 2011 04:29 AM 

Please send me detials on my below Email.

pardesifr replied on Monday, April 25, 2011 04:51 AM 

Mian sahbab,

my email

please send me the details,

especialy the detail and total price for Basement

Also please indicate area and date when it was done

JUJ replied on Monday, April 25, 2011 05:39 AM 

With basement on 10 Marlas in < 38 lakh. Is that correct?
Great post anyway.

Mian replied on Monday, April 25, 2011 07:13 AM 

Need further details send e.mail id

mach replied on Monday, April 25, 2011 07:39 AM 

my e-mail is
Miam sahib your location is Lahore or Islamabad

kamal replied on Monday, April 25, 2011 11:32 AM 

my e-mail address is. ,

Zulafqar replied on Monday, April 25, 2011 01:17 PM 

@ Mian Rashid

Please forward the details at .
Regards,

aftab01 replied on Tuesday, April 26, 2011 04:30 AM 

Main Rashid,
pls email me details.



LRE Hot Topics replied on Tuesday, April 26, 2011 06:09 AM 

Post added to useful posts list. View MORE Useful Posts Click on >>> LRE Hot Topics

Syed Soulat Abbas Zaidi replied on Saturday, April 30, 2011 03:55 PM 

i want to build 10 Marla house without basement of 5 bedrooms in Bahria Town Block A, I need your estimation if we start development in June.
Please share all the possible development costs and what cost need to be paid when so that i can arrange that amount at that time. Also duration of when the house will be ready for use?

per square feet cost is also required for clarity with material and without material.

details:
Syed Soulat Abbas Zaidi

JS replied on Tuesday, June 21, 2011 08:50 PM 

Mail me please

Waqas replied on Tuesday, November 1, 2011 09:35 AM 

I want to build 10 Marla house in Punjab Housing society near Wapda Town.

For 2 floors (without basement)
For 2 floors (with basement)

I have few construction plans in my mind. Please send me the cost accordingly.
1: If i contract with you only for labor and all material will be my responsibility.
2: If i contract with you for ever thing including labor and material

Please send me the details on the following email id so that we can proceed further:


Please keep in mind that i am planning to construct the house in next 2-3 months.

Your help in this regard is much appreciated.

Hasnain replied on Friday, November 25, 2011 03:48 PM 

Mian Sahib,

It was a very useful information. I am planning to build a 10 Marla House in Air Avenue, Lahore. I want 5 bed rooms (2 at ground level, 3 at first floor) Can you please let me know the total material needed and also the possible time it will take to complete th house. I intend to start construction in May, 2011. My email is .

Regards,
Hasnain

Qaisar Khalil replied on Friday, June 1, 2012 02:35 PM 

Mian Sahib salam,

Your information is really very usefull, i want to know the construction cost of 10 marla house with basement in lahore, kindly if u tell me the construction cost as i want to build the house in July 2012 onwards. My email add is

Qaisar Khalil replied on Friday, June 1, 2012 02:44 PM 

Mian Sahib salam,

Your information is really very usefull, i want to know the construction cost of 10 marla house with basement in lahore, kindly if u tell me the construction cost as i want to build the house in July 2012 onwards. My email add is

False flooring in Hyderab replied on Monday, June 18, 2012 05:39 AM 

Our Eco-friendly Raised flooring and Wooden false flooring is weather coated on the backside and withstands fire, water & dust. These are easy to install and are convenient for both dismantling and assembling. Owing to quality attributes, these are used in server rooms, control rooms, Hub rooms etc.
• Raised flooring are Strong Attractive, durable and long lasting
• Inspected flooring materials Our flooring experts quality.


For more details please visit http://www.falseflooring.co.in/false_flooring_in_hyderabad.php
>