A class Construction Rates,

(64592)
Sunday, April 24, 2011 07:00 AM 

On the request of many friends the enclosed tentative estimates are for 1kanal A class construction.
Variation +/-5% may occur on case-to-case basis.

Observer replied on Sunday, April 24, 2011 09:39 AM 

Thank you brother. But pls mention if these rates are current, and for which area and by which type of contractor?

Dilbar replied on Sunday, April 24, 2011 01:03 PM 

For a 20 marla (1 Kanal)home the cost is 1 cror 34 lacs 50 thousands ... I beg your pardon but I think it is high and does not seem reasonable.

Some other experts should comment on these rates.

ks replied on Sunday, April 24, 2011 02:03 PM 

Rates exactly match closely for what I am paying.

Asif replied on Sunday, April 24, 2011 03:44 PM 

Request to CMY.

Please comment whether A class construction done through LRE shall also cost same or there shall be any difference.

Fakher-ul-Hassan replied on Sunday, April 24, 2011 03:45 PM 

7500 X 1793 = 13447500/=
7500 is total covered area and 1793 is rate per sq.ft. Basement area cost Rs.200 more.

pardesifr replied on Monday, April 25, 2011 04:26 AM 

PardesiJ, the price of basement seem too expensive, as there is anothe person who posted 2-3 days back for a 10 marla plot and his price was way lower than yours, your plot required any special treatement for basement to be so costy ? 50 Lakh just for basement, that is too much, you could have constructed a new house of 10 marla in this price :S

a. moeed replied on Monday, April 25, 2011 04:32 AM 

dear bro Dilbar,plz take a breath as the amount of 1 crore 34 lacs includes constructional price for basement, ground as well as first floor.

Pardesi, Jeddah replied on Monday, April 25, 2011 05:19 AM 

My initial reaction was more harsh as I was not able to resist the temptation when I arragnged funds for the house building but the rates seemed unreasonable. I also had offers lower then this but I didn't compromise on quality as the house building is not lego blocks. As I said earlier ~+/-5% is contingent upon area & contractor.

The catch here is, as I believe, to go for the basement at these high rates at a plot lessor than 1kanal while enjoying same covered area of a normal kanal plot w/o basement; the only saving that can be achieved is from the building of Basement + its long term benefits. Lets say 5,000 to 5,200 sqft covered area at construction cost:Rs 8.5m to 9m + plot cost:Rs 4m to 4.5m totalling Rs 12.5m to 13.5m

Pardesi, Jeddah replied on Monday, April 25, 2011 06:06 AM 

If you observe closely, above is an interactive WS that allows estimation of price at different stages & their completion percentages.

If you spread out the construction period & you can arrange funds later on while finishing any one portion:
Lets say Basement & First Floor upto the Grey Structure & Ground Floor 80% complete. This requires only Rs 8.5m out of 13.5m (postpone Rs 5m) in the above example.

OR any such combination that allows you not to spend the full amount in one go.

FCA replied on Monday, April 25, 2011 06:42 AM 

Pardesi sb,
Excellent presentation (makes me wonder if you're an accountant!). It is really good to see someone sharing hard data that others can use and benefit from.

masifjamil replied on Monday, April 25, 2011 11:11 AM 

Its a good presentation. However i have experienced some higher rates especially in wood work and marble. If you choose some solid wood for doors / chokhat like Diyar, your cost would be almost double than the above rates. I also think that the cost of marble like boticena 4 sooter have been incorporated in the above sheet as the diversion to some quality marble esp 6 sooter size cost too much and your cost may be higher by Rs. 1.0 million additionally.

Adil Saeed replied on Monday, April 25, 2011 11:41 AM 

We only do A class construction jobs. We dont touch B or C class.

LRE Hot Topics replied on Tuesday, April 26, 2011 06:00 AM 

Post added to useful posts list. View MORE Useful Posts Click on >>> LRE Hot Topics

Muhammad Nasir Abbas replied on Tuesday, April 26, 2011 10:01 AM 

Dear Pardesi, Jeddah
Can you please share this excel sheet with me. My email address is m"dot"nasirabbas"at the rate of"gmail"dot"com.
Thanks in advance and may ALLAH make your house Mubarak for you & family.
Ameen.

JS replied on Tuesday, June 21, 2011 08:49 PM 

I think it is wxpensive...

Mehr Liaqat Jalvi replied on Tuesday, September 25, 2012 10:11 PM 

if someone can tell me whats is construction rate for RCC building in rural areas ?please quote me rate inclusive of (material+labour).whats is upcharge for paint/whitewash ?


cell Mehr Liaqat Jalvi
>