I had a long tiring business tour of the UK and a short & hectic personal stay in Lahore to see my dream home, the grey-structure of which is almost 90% completed (Alhamdulillah) and finally, I am back home here in Jeddah. Sorry for not contacting all the friends there because of the shortage of time.

...m ready to share the details of the house construction & the overall property market with interested friends of this forum.

AK replied on Tuesday, June 28, 2011 11:17 AM 

Congrats Pardesi,

Would appreciate if you share the details of your dream house and pictures as well.

CDW replied on Tuesday, June 28, 2011 02:06 PM 

Mubrook, and I wish you success and peace till end. I'm also going to start construction of the dream home in Phase-6 G Block, and would like to hear from you on the following:

1. Which contractor did you choose? and why? Who was doing the day-to-day supervision of your grey structure till date?

2. From where did you buy the basic material?
3. Any other advise from your experience will be appreciated.

Once again I wish you a happy living in this house once completed. Ameen.


Pardesi, Jeddah replied on Wednesday, June 29, 2011 09:36 AM 

.Living Abroad?
.Odd-sized plot?
.Ever increasing prices?
These were the questions I was facing at the beginning. I initiated the project on paper way back, before the actual on-the-ground spade-work started, by taking the actual dimensions within the society's regulations. I plotted inch by inch over MSVisio to my satisfaction & also on the SweetHome3d as a rough sketch for a 3D walk -through. All in all I designed 33 versions, floor-by-floor comparing & matching to my requirements & pocket. Fine tuning did by the architect.

Then I searched for the contractor; interestingly, I met some good people in the business when I went to Lahore last year. I found that taking pains of procuring material, its security & managing labour is a full time specialized job. I shared the construction estimates on this forum 2/3 months back which proved that technical problems in building a basement, its insulation & drainage and fine tuning of the design needs specialized capabilities; plus, for a project involving millions of rupees you MAY save 2/3 lacs if you have time & expertise but I did the other way & contracted for the grey-structure, architectural elevation, designing with material & supervision. I have found the person honest & co-operative; although satisfaction is a relative term but I think I could not do better than what I have achived Be-Hamdillah. I have sent you the details of the contractor via email.

Masha-Allah, it is at 14marla, around 5,000 sq. ft. covered area in the Suigas Society Ph1 and has:
. 3 Beds attached dressing/bath, lounge, & a store in the basement with 2 patios open to sky;
. 2 beds attached dressing/bath, lounge, drawing, kitchen with serving kitchen & a car porch at the ground floor;
. 2 beds attached dressing/bath, lounge, drawing, kitchen, laundry, balcony & 2 terraces at the independently separable first floor.

I am now planning for the finishing phase let this monsoon be over Insha-Allah.

A Request: Friends with experience of finishing to share their experiences.

AK replied on Wednesday, June 29, 2011 09:55 AM 

@Pardesi...

Can you please share the rate for grey structure contract with material?
Did you decide brand of things like Cement, Iron bars etc.?
How much time it took? Did you go for RCC column beam structure? How much steel bar is used?

Pardesi, Jeddah replied on Wednesday, June 29, 2011 10:30 AM 

Replies @AK

Can you please share the rate for grey structure contract with material? Rs. 1,000+
Did you decide brand of things like Cement, Iron bars etc.? YES
How much time it took? 6 MONTHS
Did you go for RCC column beam structure? NO
How much steel bar is used? 15+tons but not sure, need to ask my contractor.

AK replied on Wednesday, June 29, 2011 03:15 PM 

Thanks Pardesi for prompt reply...

Overseas Pakistani replied on Thursday, June 30, 2011 06:21 AM 

Padresi ji,

Would be grateful if you could please share the details of contractor / Architec / Supervising Agents followed by the rates and contact numbers on this e-mail ID .

Appreciate your assistance.

Overseas Pakistani replied on Thursday, June 30, 2011 06:26 AM 

>