Dear CMY, I hope and pray for the best of all in this Ramadaan.
Any update on the inauguration of Phase 5/6 interchange on Ring road as it was planned on 31st July. Kindly can you upload the video of Ph 5 Sector C also ?
Best regards Baba Ji replied on Monday, August 8, 2011 04:55 AM
My apologies ... I meant Ph 6 sector C ... |
Lahore Ring Road replied on Monday, August 8, 2011 06:20 AM
Work on Lahore Ring road have been slowed mainly due to shortage of funds. Lahore ring road up to DHA 8 interchange is now complete and open for traffic. DHA 8 to DHA6 part of Lahore ring road is now ready for black top. Some parts have been black topped. Interchange on DHA 5 / 6 of Lahore ring road is 90% complete. Within two to four weeks they may start land scapping work here and within month or max upto Sept 30th State Life 1 to Moterway all parts of Lahore ring road should open for traffic. Ch Mujahid Yasin ( CMY ) 03224009967 |