Kindly inform me the rates of construction material & labour rates in Rawalpindi Islamabad area:
Bricks
Steel
Cement
Crush
Sand etc.
Labour rates
Tesi Kandi covered area
Tesi Kandi covered area+ extra area works
Than you all jk replied on Sunday, December 18, 2011 01:54 PM
Bricks 7000 TO 8500 PER 1000 Steel 68000 TO 72000 PER TONE Cement 395 TO 405 PER 50 KG BAG Crush 25 per sq ft Sand etc. 22 per sq ft Labour rates 210 per Sq.ft Tesi Kandi covered area Tesi Kandi covered area+ extra area works |
jk replied on Sunday, December 18, 2011 01:56 PM
Correction please Crush and Sand rates are per cubic feet and not sq.ft |
Pardesi log replied on Monday, December 19, 2011 06:34 AM
Dear Jk thank u for ur reply, but please let me know the reason of variation in prices whether based on quality of material or only dealer to dealer Bricks 7000/1000 for which quality and 7500/1000 for which and 8500/1000 for what? steel 68000/ton for which company and 72000/ton for what brand? Cement 395 for which Compnay and 405 for which brand? Thank u once again |
A.Akram replied on Monday, December 19, 2011 10:56 PM
Brothers, Can you please advice that how much material (No. of Bricks, cement bags, steel etc.) is required for a standard 10 Marla house of 2800 sq. ft. Thanks. |
Ahmad replied on Tuesday, December 20, 2011 02:54 AM
Dear JK Sahib, Sir I have a question regarding roof heat insulation. Do you recommend BOARD and what thickness is good for Lahore weather? Also can you please send me your email at Thanks |
jk replied on Tuesday, December 20, 2011 08:41 AM
Dear Ahmed, Proper water proofing and roof insulation is very expensive item and not advised to spend much on this issue as it is not the only roof that brings in heat but single core walls and windows as well. I will suggest to lay roof with very minor slop so that water does not stand on and then use gypsum false ceiling as it gives decoration and prevent heating too. |