Dear All
I have a 10 M plot and now want to construct a double story house. I am in search of a good contarctor now a days who can work on labor rate.
Can anybody tell me how to prepare schedule of payment if the labor rate is 140 becuase one of my friend told me that be very carefull before deciding how to make payment to contractor on different phases ( i,e how much to pay up to foundation, brickwork, lenter etc) to avoid any future conflicts.
Need your advice.
Thanks in advance
Muhammad Hamza contrctorpaymentplan replied on Sunday, March 25, 2012 10:10 AM
140.....? that is really low, anywayz best of luck :) this schedule might help you in deciding! G.F: 1) Advance 10% 2) DPC level 10% 3) Walls 7' 10% 4) Walls 10' 5% 5) Lintel 20% 6) Internal plaster 10% 7) floor pcc 5% 8) boundary wall 10% 9) marble/tiles/slabs complete etc 15% 10)Final 5% |
contrctorpaymentplann replied on Sunday, March 25, 2012 10:16 AM
F.F: 1) walls 7' 10% 2) walls 10' 10% 3) lintel 20% 4) Internal plaster 10% 5) External plaster 15% 6) floor pcc 5% 7) marble/tiles/slabs complete etc 15% 8) Roof tiles and water proofing complete 10% 9) Final 5% Regards:) |