Can anyone
update me the development condition of f-15 extention and i-11 CDA Islamabad and when is expected to have possession and develoopment?
Thank you.
Dr.Khalid
Rana replied on Monday, March 1, 2010 04:28 PM PST
Dr sahib why do you keep asking the same question again & again it has been answered before when you asked, please go back pages to have look.
atiq raja. replied on Monday, March 1, 2010 11:20 PM
both are not CDA sectors.
Mian Nadeem Islamabad replied on Wednesday, March 3, 2010 10:38 AM PST
I-11 is CDA sector, I-11/3 & I-11/4 Commercial and I-11/1 & I-11/2 residential. Atiq bhai u are wrong.
CDA has invited contractors for pre-qualification for start of development work in I-11/1 & I-11/2. Project cost 250 million last date 18 march.If dispute resolved with locals work will start in May.
Dispute with old residents is main cause of delay they are demanding more plots against their land .CDA has already allotted 2400 plots in
I-12.
Pray that CDA managed to start work.